Why road construction is slow– Lagos 4 years ago 3

The Lagos State Government on Sunday said the reconstruction of the Ago Palace Way, Okota, was delayed by litigations and other factors which had been addressed.

According to a statement by the Assistant Director, Press and Public Relations, Ministry of Works and Infrastructure, Biola Fagunwa, the area is a strategic bypass that links the Expressway to Amuwo Odofin and Festac Town.

It also opened up an alternative route from Festac/Amuwo to Ikotun, Ejigbo, Egbeda and Oshodi.

The state government said it was aware of concerns about the slow pace of road construction in the area and its impact such as cost of transportation, gridlock, non-availability of alternative routes and fear of flooding.

It assured residents that effort were being made to finish the road on time.

The statement read, “As an existing road in a developed area, there is bound to be removal of some structures. However, government has paid adequate compensation to those with legally tenable claims.

“The agreed construction work plan submitted by the construction company handling the work indicates that the drainage channels are to be done prior to proper road construction. This has been done except in the area where litigations have stalled completion.”

The government urged people in the area to see their inconveniences as prices being paid for modernisation of the area.

“Wherever there is an ongoing construction, the ministry provides alternative routes. This has been done on this project as in all other road projects,” the statement said.

It added that the commissioner for the ministry, Obafemi Hamzat, had visited the area and other palliatives measures were being worked out. Home Page